CST Cheat Sheet 2026
The 30 highest-yield CST facts, distilled from real exam questions. Print it, save it as a PDF, or study it here โ free, no sign-up.
CST exam key facts
- The Certified Scheduling Technician exam consists of 100 simple multiple-choice questions. Source
- The Certified Scheduling Technician examination has a maximum time limit of 3 hours. Source
- An overall score of 70% or higher is required to pass the Certified Scheduling Technician exam. Source
- The Certified Scheduling Technician examination fee is US$260 for AACE members and US$390 for non-members. Source
- Once cleared by AACE, candidates have six months to take the CST exam up to three times. Source
- The Certified Scheduling Technician certification is valid for 4 years. Source
100 questions
180 min time limit
70.00% to pass
- What does a Work Breakdown Structure (WBS) help with? โ Breaking down project tasks into smaller components
- What is the purpose of a 'resource calendar' in a resource-loaded schedule? โ To define when each resource is available, including vacations and holidays
- Why are cloud-based scheduling tools advantageous? โ They provide real-time collaboration and accessibility
- When applying fast-tracking, which type of dependency is most commonly modified? โ Discretionary finish-to-start dependencies
- In schedule risk analysis, what does a 'three-point estimate' consist of? โ Optimistic, most likely, and pessimistic duration estimates for an activity
- What is the relationship between the Authorized Work (AW) and the Performance Measurement Baseline (PMB) in a government EVM system? โ AW equals PMB plus management reserve
- Which quality assurance method is most commonly applied in cost-loaded schedule integration to verify that CST professional standards are being met? โ Structured audits, peer reviews, and performance metrics aligned with industry benchmarks
- What scheduling document is commonly required by public agency contracts to substantiate a contractor's request for a time extension? โ A contemporaneous schedule delay analysis using the accepted project schedule
- What is the primary ethical obligation of a CST professional when a conflict of interest arises during resource loading & leveling activities? โ Disclose the conflict to all relevant parties and recuse from the decision if necessary
- Which of the following is a fundamental principle of cost-loaded schedule integration as it applies to Certified Scheduling Technician? โ Systematic evaluation and adherence to established industry standards
- Which lag type applied to a milestone predecessor relationship would delay a milestone by 2 weeks after its predecessor finishes? โ Positive lag of 2 weeks on a Finish-to-Start link
- Which AACE International Recommended Practice is specifically associated with forensic schedule analysis and delay claim methodologies? โ RP 29R-03
- A schedule network shows that Activity C can start as soon as Activity A is 50% complete. This is modeled as a: โ Start-to-start relationship
- Which of the following is a primary risk associated with fast-tracking? โ Increased rework if errors in overlapped activities propagate downstream
- The 'But For' analysis in schedule delay disputes attempts to answer: โ What would the schedule look like but for the alleged delay event?
- Which quality assurance method is most commonly applied in critical path & float analysis to verify that CST professional standards are being met? โ Structured audits, peer reviews, and performance metrics aligned with industry benchmarks
- Which scheduling concept specifically uses milestones as weighted events to measure physical percent complete in government contracts? โ Milestone Weighted Method (MWM)
- Which Integrated Baseline Review (IBR) objective verifies that the cost-loaded schedule is achievable given available resources? โ Validate that the PMB is realistic, executable, and adequately resourced
- In Microsoft Project, what does the 'Peak' field in a resource usage view represent? โ The maximum units allocated to a task in any single time period
- A project schedule shows a Schedule Performance Index (SPI) of 0.75. This means the project is: โ 25% behind schedule โ only 75 cents of work done per $1 planned
- Which document outlines who is responsible for each project task? โ Responsibility Assignment Matrix (RAM)
- In Primavera P6, which earned value calculation method computes BCWP based on the physical percent complete entered by the user? โ Physical Percent Complete
- Which risk response strategy involves adding parallel activities to reduce schedule risk? โ Fast-tracking
- What is a milestone in project scheduling? โ A major event or achievement in the project
- In schedule compression, crashing differs from fast tracking in that crashing: โ Adds resources to critical path activities to shorten duration
- What is a primary benefit of using scheduling software? โ Increases scheduling efficiency and accuracy
- What is the purpose of a project schedule? โ To plan and track project activities and deadlines
- What is the primary ethical obligation of a CST professional when a conflict of interest arises during p6 & ms project proficiency activities? โ Disclose the conflict to all relevant parties and recuse from the decision if necessary
- A project schedule network diagram that shows all activities as nodes connected by arrows representing dependencies is using which method? โ Precedence Diagramming Method (PDM)
- In Monte Carlo simulation for schedule risk analysis, what does the P80 date represent? โ The date by which there is an 80% probability of completing the project
Turn these facts into recall:
What Practice Test Geeks adds beyond an AI chat for CST
An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:
- A timed, full-length CST mock exam โ 100 questions in 180 minutes with a 70% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
- A fixed CST question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
- Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
- CST flashcards built from the same question bank.
- Free CST practice tests with the correct answer shown after each question.
Was this helpful?
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- web.aacei.org โ Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit ยท verified Oct 2026