A Product Owner arrives at Sprint Planning with a prioritized Product Backlog but has not refined any items with the Development Team beforehand. What is the most likely outcome?
-
A
Sprint Planning will be cancelled by the Scrum Master
-
B
The team may struggle to create a realistic Sprint Goal and forecast
-
C
The team must accept the top items regardless of clarity
-
D
The Scrum Master should refine the backlog on behalf of the team