In Primavera P6, which scheduling option controls whether a project is scheduled from its planned start date or its data date?
-
A
Schedule From: Project Planned Start or Data Date
-
B
Auto Schedule toggle
-
C
Project Must Finish By constraint
-
D
Baseline Lock setting