A new Scrum Team insists on planning two Sprints at once to 'reduce overhead.' How should a CST respond?
-
A
Allow it since the team is self-organizing
-
B
Explain that Sprint Planning is time-boxed per Sprint to maintain inspect-and-adapt cycles
-
C
Suggest combining retrospectives as well for efficiency
-
D
Escalate to the Product Owner for a decision