A project's actual progress curve falls below its planned S-curve. When analyzing this with EVM, which metric directly quantifies this gap in cost units?
-
A
Cost Variance (CV)
-
B
Schedule Variance (SV)
-
C
Schedule Performance Index (SPI)
-
D
Variance at Completion (VAC)