A project reports SV = -$15,000 and SPI = 0.82. What do these metrics collectively indicate?
-
A
The project is under budget and ahead of schedule
-
B
The project is behind schedule and completing less work than planned per dollar spent
-
C
The project is over budget but on schedule
-
D
The project has a positive cost variance offsetting schedule delays