When fast-tracking introduces a start-to-start relationship with a lag, what does the lag represent?
-
A
The amount of total float remaining on the activity
-
B
The minimum required delay before the successor activity can begin after its predecessor starts
-
C
The crash cost associated with accelerating the activity
-
D
The peak resource demand for the overlapped activities