What is the purpose of a 'resource calendar' in a resource-loaded schedule?
-
A
To track actual hours worked by each resource
-
B
To define when each resource is available, including vacations and holidays
-
C
To assign resources to specific work packages
-
D
To calculate earned value for resource costs