The 'Definition of Ready' (DoR) is sometimes used to gatekeep items entering a Sprint. What is the main risk of enforcing a strict DoR?
-
A
It eliminates all ambiguity from Sprint Planning
-
B
It can become a bureaucratic barrier that slows delivery and violates Scrum's empirical nature
-
C
It prevents the Developers from collaborating with the Product Owner
-
D
It makes Sprint Retrospectives unnecessary