In MS Project, what is the result of setting a task's 'Task Type' to 'Fixed Work' and then changing its duration?
-
A
Duration changes and Work stays constant, so resource Units adjust automatically
-
B
Work changes proportionally while Units remain fixed
-
C
Both Work and Units remain unchanged; only the calendar span is extended
-
D
The task is converted to a milestone automatically