In MS Project, what is the effect of linking tasks with a 'Start-to-Start' (SS) dependency with a 3-day lag?
-
A
The successor must finish 3 days after the predecessor finishes
-
B
The successor cannot start until 3 days after the predecessor starts
-
C
The successor must start 3 days before the predecessor starts
-
D
The successor is delayed by 3 days from the project start date