In Oracle Primavera P6, what does the 'Retained Logic' progress override setting do when activities are out of sequence?
-
A
It ignores predecessor constraints for in-progress activities
-
B
It retains the original logic and delays successor start until the predecessor finishes
-
C
It automatically removes all open-ended activities
-
D
It converts all finish-to-start links to start-to-start links