When converting an Arrow Diagramming Method (ADM) network to a Precedence Diagramming Method (PDM) network, dummy activities are:
-
A
Converted to SS relationships with zero lag
-
B
Eliminated because PDM uses node-based logic to capture dependencies directly
-
C
Converted to mandatory milestones in PDM
-
D
Retained as zero-duration activities to preserve logic