In a cost-loaded schedule, what does the Performance Measurement Baseline (PMB) represent?
-
A
The sum of all contract change orders approved to date
-
B
The time-phased budget plan against which project performance is measured
-
C
The actual costs incurred through the data date
-
D
The estimated cost at completion based on current performance