CST Baseline & Earned Value Schedule 2

Free ยท Instant Results

A project has a Budget at Completion (BAC) of $200,000. At the status date, the Earned Value (EV) is $80,000 and the Actual Cost (AC) is $100,000. What is the Cost Variance (CV)?