What is the primary advantage of using story points rather than hours for estimating in Scrum?
-
A
They satisfy stakeholder reporting requirements more efficiently
-
B
They enable relative estimation that is team-specific and avoids time-pressure anchoring
-
C
They align with PMI estimation standards for project management
-
D
They allow the Product Owner to assign work to individual developers