What is a 'Time Impact Analysis' (TIA) and when is it typically used?
-
A
A schedule analysis method used to evaluate the impact of a change or delay event on the project completion date
-
B
A technique for measuring earned value on time-based contracts
-
C
A process for accelerating the schedule using overtime
-
D
A method for comparing actual vs. planned resource utilization