Resource Loading & Leveling Flashcards
7 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Resource Loading & Leveling flashcards as text
What is 'resource contention' in project scheduling?
Answer: Two or more activities competing for the same limited resource simultaneously
Resource contention occurs when multiple activities require the same resource at the same time, exceeding its available capacity.
Which of the following best describes 'resource pooling' as a leveling strategy?
Answer: Sharing interchangeable resources across activities to balance demand
Resource pooling uses interchangeable resources flexibly across activities to balance workloads and reduce over-allocation.
In a resource-loaded schedule, which document type shows each resource's assigned hours broken down by time period?
Answer: Resource usage spreadsheet or time-phased resource plan
A time-phased resource plan or resource usage spreadsheet shows hours per resource per time period across the schedule.
A project has a resource with 120 hours of work assigned in a 80-hour (two-week) period. What is the over-allocation percentage?
Answer: 50%
120 hours assigned against 80 hours available equals 150% utilization, or 50% over-allocation above the 100% baseline.
When leveling resources across multiple projects in a portfolio, what is the primary complexity that single-project leveling does not face?
Answer: Resources must be shared across competing project priorities simultaneously
Portfolio-level leveling must balance competing priorities across projects, requiring decisions about which project's activities get resource access first.
What scheduling output provides the most direct input for creating a resource loading chart?
Answer: Activity list with resource assignments and time-phased schedule
The time-phased schedule with resource assignments shows which resources are needed at which times, directly driving the loading chart.
Which technique involves adding resources to an over-allocated activity to shorten its duration and reduce the contention period?
Answer: Crashing
Crashing adds resources to shorten activity duration, potentially reducing or eliminating the over-allocation window.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- web.aacei.org — Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit · verified Oct 2026