CST Schedule Risk & Contingency Analysis Flashcards

6 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 CST Schedule Risk & Contingency Analysis flashcards as text
  1. What is the primary purpose of a schedule risk analysis (SRA) in project scheduling?

    Answer: To identify potential schedule delays and quantify their probability and impact

    An SRA identifies risks that could cause delays and uses probabilistic methods to quantify their likelihood and effect on the project completion date.

  2. In Monte Carlo simulation for schedule risk analysis, what does the P80 date represent?

    Answer: The date by which there is an 80% probability of completing the project

    The P80 date is the date at which there is an 80% statistical confidence that the project will be completed, based on simulated schedule outcomes.

  3. What is a schedule contingency reserve?

    Answer: Extra time added to the schedule to account for identified and unidentified risks

    A schedule contingency reserve is additional time built into the schedule to mitigate the impact of risks that may materialize during project execution.

  4. Which risk response strategy involves adding parallel activities to reduce schedule risk?

    Answer: Fast-tracking

    Fast-tracking overlaps activities that were originally planned in sequence, compressing the schedule and reducing the risk of late completion.

  5. What is the 'near-critical path' in the context of schedule risk?

    Answer: Activities with small amounts of total float that could become critical if delays occur

    Near-critical paths contain activities with minimal float that pose significant risk of becoming critical if delays occur, making them important to monitor during risk analysis.

  6. When performing a qualitative schedule risk assessment, which matrix is commonly used to prioritize risks?

    Answer: Probability and Impact matrix

    The Probability and Impact matrix ranks risks by multiplying the likelihood of occurrence by the severity of the schedule impact, allowing prioritization of the most significant risks.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. web.aacei.org — Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit · verified Oct 2026
CST Schedule Risk & Contingency Analysis Flashcards — CST Study Cards with Answers