CST Schedule Risk & Contingency Analysis Flashcards
6 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 CST Schedule Risk & Contingency Analysis flashcards as text
What AACE International recommended practice provides guidance on schedule risk analysis?
Answer: AACE RP 57R-09
AACE RP 57R-09 provides a framework for integrated cost and schedule risk analysis, including Monte Carlo simulation methods for project schedules.
In schedule risk analysis, what does a 'three-point estimate' consist of?
Answer: Optimistic, most likely, and pessimistic duration estimates for an activity
A three-point estimate uses optimistic (O), most likely (M), and pessimistic (P) durations to model activity duration uncertainty for risk analysis.
What is schedule risk exposure?
Answer: The product of the probability of a risk event occurring and its schedule impact in days
Schedule risk exposure quantifies the expected schedule impact of a risk by multiplying its probability of occurrence by the number of days of delay it would cause.
Which technique involves deliberately planning workarounds in advance for risks that have high probability and high schedule impact?
Answer: Contingency planning
Contingency planning creates predefined response strategies (workarounds) for high-probability, high-impact risks so that the team can react quickly if those risks materialize.
In a Monte Carlo schedule simulation, what does a wider spread in the S-curve output indicate?
Answer: Greater uncertainty and risk in the schedule
A wider S-curve spread in Monte Carlo output indicates that the range of possible completion dates is large, reflecting higher schedule uncertainty and risk.
What is the purpose of a 'risk register' in schedule risk management?
Answer: To document identified risks, their probability, impact, and response strategies
The risk register is a project document that captures all identified risks along with their probability, potential schedule impact, and planned mitigation or contingency responses.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- web.aacei.org — Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit · verified Oct 2026