← All CST Flashcard Decks

Baseline & Earned Value Schedule Flashcards

7 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Baseline & Earned Value Schedule flashcards as text
  1. When analyzing schedule health using EVM, a negative Schedule Variance (SV) combined with an SPI less than 1.0 most likely indicates:

    Answer: The project is behind schedule and performing less work than planned

    Both negative SV and SPI < 1.0 confirm the project is completing less work than planned, indicating a schedule delay.

  2. A project baseline change is sometimes called a 'baseline re-plan.' Under what condition is a re-plan considered inappropriate?

    Answer: When management wants to hide past schedule variances without an approved change

    Re-planning to conceal unfavorable variances without an approved change ('rubber baseline') is a misuse of the baseline process.

  3. What is the relationship between the Authorized Work (AW) and the Performance Measurement Baseline (PMB) in a government EVM system?

    Answer: AW equals PMB plus management reserve

    Total Authorized Work (AW) = PMB + Management Reserve; management reserve is held outside the PMB for unplanned scope.

  4. On a project, the actual finish date of an activity is earlier than the baseline finish date. This is referred to as:

    Answer: A baseline deviation with positive schedule variance

    When actual completion precedes the baseline date, this is a positive schedule variance or baseline deviation indicating the work finished early.

  5. Under ANSI/EIA-748 EVMS guidelines, how frequently must contractors report EVM data to the government on large contracts?

    Answer: Monthly

    ANSI/EIA-748 requires monthly reporting of cost and schedule performance data via the Contract Performance Report (CPR).

  6. What is 'undistributed budget' (UB) in the context of an EVM system?

    Answer: Authorized budget not yet assigned to a specific control account

    Undistributed Budget (UB) is authorized budget that has not yet been formally distributed to control accounts within the WBS/OBS.

  7. A project schedule baseline includes all of the following EXCEPT:

    Answer: Actual cost expenditures to date

    The schedule baseline captures planned dates, milestones, and float values, but actual costs belong to the cost baseline and financial records, not the schedule baseline.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. web.aacei.org — Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit · verified Oct 2026