  1. The Estimate to Complete (ETC) assumes all future work will be performed at the budgeted rate. Which formula represents this?

    Answer: ETC = BAC - EV

    ETC = BAC - EV assumes the remaining work will be completed at the originally planned cost efficiency (CPI = 1.0).

  2. Which of the following would NOT typically trigger a formal baseline revision?

    Answer: Weekly schedule status updates

    Weekly status updates reflect current performance against the baseline but do not themselves constitute a reason to change the baseline.

  3. On a project with BAC = $500,000, EV = $200,000, and AC = $250,000, what is the CPI?

    Answer: 0.80

    CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning only 80 cents of value is being earned per dollar spent.

  4. A control account is the management control point in EVM where which two elements are integrated?

    Answer: Scope and cost against a time-phased plan

    Control accounts integrate scope and cost into a time-phased plan, enabling earned value measurement at a manageable level.

  5. What does a Variance at Completion (VAC) of -$30,000 indicate?

    Answer: The project is expected to overrun its budget by $30,000

    VAC = BAC - EAC; a negative VAC means the Estimate at Completion exceeds the Budget at Completion, projecting a cost overrun.

  6. In a time-phased budget, the cumulative Planned Value (PV) curve is commonly referred to as what shape?

    Answer: S-curve

    The cumulative PV baseline typically forms an S-curve, starting slow, accelerating through mid-project, and tapering near completion.

  7. Which earned value method assigns 50% credit at start and 50% upon completion, suitable for short-duration tasks?

    Answer: 50/50 rule

    The 50/50 rule grants 50% earned value when work begins and the remaining 50% upon task completion, useful for activities spanning one reporting period.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. web.aacei.org — Test delivery, exam format, retake policy, score release, eligibility, fees, passing score, renewal, retake fee, time limit · verified Oct 2026