Sprint Planning and Execution Flashcards
6 cards from real CSM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Sprint Planning and Execution flashcards as text
What is the recommended Sprint length according to the Scrum Guide?
Answer: One month or less
Sprints are one month or less in duration; shorter Sprints reduce risk by generating feedback and enabling adaptation more frequently.
Can the Sprint Goal be changed once a Sprint has started?
Answer: No, the Sprint Goal should not be changed during the Sprint
The Sprint Goal is a commitment that should not change during the Sprint; it provides the stability the Developers need to focus.
What should a Scrum Team do if they complete their Sprint Backlog work before the Sprint ends?
Answer: Collaborate with the Product Owner to pull in more work from the Product Backlog
If a team finishes early, they should work with the Product Owner to bring additional Product Backlog items into the Sprint that align with the Sprint Goal.
What defines an Increment in Scrum?
Answer: A concrete stepping stone toward the Product Goal that meets the Definition of Done
An Increment is a concrete stepping stone toward the Product Goal and must meet the Definition of Done to be considered releasable.
What happens to unfinished Sprint Backlog items at the end of a Sprint?
Answer: They are returned to the Product Backlog for re-ordering
Unfinished items are returned to the Product Backlog, where the Product Owner re-orders them based on current value and priority.
Multiple Increments may be created within a single Sprint.
Answer: True
Multiple Increments can be created during a Sprint, and each must meet the Definition of Done; they may be delivered to stakeholders before the Sprint Review.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- support.scrumalliance.org — Renewal, eligibility, test delivery, exam format, retake policy, test dates, time limit, retake fee · verified Nov 2026
- scrumalliance.org — Fees, passing score, score validity · verified Oct 2026