What is the purpose of the Sprint Review?
Answer: To inspect the Increment and adapt the Product Backlog based on stakeholder feedback
The Sprint Review is an inspection of the Increment and adaptation of the Product Backlog; it is a working session where the Scrum Team and stakeholders collaborate on next steps.
Who participates in the Sprint Review?
Answer: The Scrum Team and invited stakeholders
The Sprint Review includes the entire Scrum Team and key stakeholders invited by the Product Owner to collaborate on what was built and what comes next.
What is the difference between velocity and capacity in Scrum?
Answer: Velocity is historical throughput; capacity is available time/effort for a Sprint
Velocity is a historical measure of work completed per Sprint, while capacity refers to the available working time and effort Developers have in an upcoming Sprint.
What is the purpose of story point estimation in Scrum?
Answer: To provide relative size estimates that support forecasting without over-committing to time
Story points provide a relative measure of effort and complexity that helps teams forecast throughput without locking in specific time estimates for each item.
How does empiricism support continuous improvement in Scrum?
Answer: By using transparency, inspection, and adaptation to learn and adjust regularly
Scrum's empirical approach relies on transparency, inspection, and adaptation so teams continuously learn from real outcomes and adjust their practices accordingly.
What is the Sprint Review time-box for a one-month Sprint?
Answer: 4 hours
The Sprint Review is time-boxed to 4 hours for a one-month Sprint, with shorter Sprints typically having proportionally shorter reviews.