A deferred submittal is best described as a submittal that is:
-
A
Submitted late due to contractor negligence
-
B
Approved in advance but held until later phases
-
C
Intentionally postponed to a later phase with the design professional's prior approval
-
D
Rejected and deferred to the next project phase