Which project delivery method typically results in the shortest overall project duration when schedule is the primary driver?
-
A
Design-Bid-Build
-
B
Design-Build with fast-track scheduling
-
C
Multiple Prime Contracting
-
D
Competitive sealed bidding with addenda