When an architect issues a Supplemental Instruction (ASI), what is the primary characteristic that distinguishes it from a Change Order?
-
A
It requires the owner's written approval
-
B
It involves no change in contract sum or time
-
C
It must be signed by the contractor
-
D
It applies only to structural modifications