โ† All CSI Flashcard Decks

Contract Administration & Communication Flashcards

6 cards from real CSI practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 Contract Administration & Communication flashcards as text
  1. What is the primary function of contract administration during construction?

    Answer: Oversee work in line with contract documents

    Contract administration ensures that construction is completed in accordance with contract documents and specifications.

  2. What is a submittal in the context of contract administration?

    Answer: Sample or document confirming material compliance

    Submittals include product data, shop drawings, and samples submitted for approval to confirm compliance with specs.

  3. Which document records changes to the scope, cost, or schedule of a construction project?

    Answer: Change order

    Change orders formally document modifications to contract terms, including scope, cost, or schedule.

  4. What is the purpose of a Request for Information (RFI)?

    Answer: Clarify project documents

    RFIs are used to clarify details in the construction documents when uncertainties arise during the build.

  5. Which party typically reviews and approves submittals?

    Answer: Architect or engineer

    The architect or engineer reviews submittals to ensure compliance with project specifications and design intent.

  6. How is effective communication maintained during construction?

    Answer: Through formal records and meetings

    Clear documentation, scheduled meetings, and timely RFIs help keep all parties aligned and informed.