โ† All CSI Flashcard Decks

Construction Documents & Specifications Flashcards

7 cards from real CSI practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Construction Documents & Specifications flashcards as text
  1. What is the correct MasterFormat division for mechanical plumbing systems?

    Answer: Division 22

    Division 22 - Plumbing covers all plumbing systems including piping, fixtures, and domestic water systems.

  2. A contractor submits a shop drawing that deviates from the contract documents. The architect reviews and stamps it 'Approved as Noted.' What does this mean?

    Answer: The contractor may proceed only if the noted corrections are incorporated

    'Approved as Noted' means the submittal is conditionally accepted provided the contractor incorporates all reviewer comments before fabrication or installation.

  3. Which document formally modifies the contract sum or contract time after contract execution?

    Answer: Change Order

    A Change Order is the only document that officially modifies the contract sum and/or contract time after the agreement has been signed.

  4. What does 'imperative mood' mean in the context of specification writing style?

    Answer: Using direct commands without naming the subject (e.g., 'Install,' 'Provide')

    Imperative mood uses command verbs without restating the subject (contractor), making specifications more concise and direct.

  5. A specification section's PART 2 - PRODUCTS article on 'Mixes' would most likely appear in which type of section?

    Answer: Concrete

    Cast-in-place concrete specifications include a Mixes article detailing the proportioning of cement, aggregate, water, and admixtures.

  6. The term 'project closeout' in Division 01 encompasses which of the following?

    Answer: Final cleaning, record documents, operation manuals, and warranties

    Project closeout requirements in Division 01 cover final cleaning, as-built/record documents, O&M manuals, warranties, and substantial/final completion procedures.

  7. Which CSI format organizes cost data by physical building components rather than by construction trades?

    Answer: UniFormat

    UniFormat organizes information by functional building elements (e.g., foundations, exterior walls) regardless of the materials or trade involved.