During project execution, a team member raises a concern that a deliverable does not meet the specified requirements. The project manager should first:
-
A
Immediately notify the sponsor of the defect
-
B
Review the quality standards and verify the requirements against the deliverable
-
C
Assign blame to the team member responsible
-
D
Submit a change request to modify the requirements