CSET Project Planning & Execution 3 — Questions and Answers
Question 1: During which project phase are lessons learned most effectively documented?
- Initiating
- Planning
- Executing
- Closing (Correct answer)
Correct answer: Closing
While lessons learned should be captured throughout, they are formally documented and archived during the project closing phase.
Question 2: A project manager uses a probability-impact matrix primarily to:
- Assign tasks to team members
- Prioritize identified risks for response planning (Correct answer)
- Determine the project's critical path
- Allocate the project budget
Correct answer: Prioritize identified risks for response planning
A probability-impact matrix ranks risks by combining their likelihood and potential impact, helping prioritize which risks need response plans.
Question 3: Which estimating technique uses historical data from a similar past project to estimate the current project's duration or cost?
- Bottom-up estimating
- Analogous estimating (Correct answer)
- Parametric estimating
- Three-point estimating
Correct answer: Analogous estimating
Analogous estimating leverages actual duration or cost data from a similar previous project as the basis for the current estimate.
Question 4: In Agile project management, a 'velocity' metric measures:
- The speed of individual developer task completion
- The amount of work a team completes in a sprint (Correct answer)
- The project's overall progress against the timeline
- The number of defects found per sprint
Correct answer: The amount of work a team completes in a sprint
Velocity measures the average number of story points or work units completed by a team in a single sprint, used to forecast future output.
Question 5: What is the primary purpose of a project kickoff meeting?
- To finalize the project budget
- To align all stakeholders on project goals, roles, and expectations (Correct answer)
- To create the project schedule
- To perform the first project risk assessment
Correct answer: To align all stakeholders on project goals, roles, and expectations
A kickoff meeting brings together key stakeholders to establish shared understanding of project objectives, deliverables, roles, and processes.
Question 6: When a project manager applies 'fast tracking,' they are:
- Cutting project scope to meet a deadline
- Performing activities in parallel that were originally planned sequentially (Correct answer)
- Adding more resources to compress the schedule
- Using automated tools to speed up reporting
Correct answer: Performing activities in parallel that were originally planned sequentially
Fast tracking compresses the schedule by overlapping phases or tasks that would normally be done in sequence, which increases risk.
Question 7: A stakeholder register is used to:
- Track project expenses by department
- Document stakeholder information, interests, and engagement levels (Correct answer)
- Record meeting minutes for compliance
- Assign tasks to project team members
Correct answer: Document stakeholder information, interests, and engagement levels
The stakeholder register captures identifying information, roles, interests, expectations, and influence levels of all project stakeholders.
During which project phase are lessons learned most effectively documented?