Which of the following is the BEST example of a 'pull' communication method?
-
A
Sending a project update email to all stakeholders
-
B
Posting project documents on a shared intranet portal for stakeholders to access on demand
-
C
Calling a stakeholder directly to share a critical risk
-
D
Presenting a status update at a monthly steering committee meeting