← All CSET Flashcard Decks

Risk Assessment & Management Flashcards

7 cards from real CSET practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Risk Assessment & Management flashcards as text
  1. A school district identifies that a new software system could fail during high-stakes testing. Which risk response strategy involves purchasing cybersecurity insurance to cover potential losses?

    Answer: Risk transfer

    Risk transfer shifts the financial consequences of a risk to a third party, such as an insurance provider.

  2. During a quantitative risk analysis, a project manager calculates Expected Monetary Value (EMV). If an event has a 30% probability of occurring and would cost $50,000, what is its EMV?

    Answer: $15,000

    EMV is calculated by multiplying the probability (0.30) by the impact ($50,000), yielding $15,000.

  3. Which risk analysis technique uses optimistic, pessimistic, and most likely estimates to model uncertainty in project timelines?

    Answer: PERT analysis

    PERT (Program Evaluation and Review Technique) uses three-point estimates to calculate expected durations under uncertainty.

  4. A risk register entry shows a risk with HIGH likelihood and LOW impact. How should this risk be prioritized compared to a risk with LOW likelihood and HIGH impact?

    Answer: Prioritization depends on the calculated risk score for each

    Risk prioritization is based on the overall risk score (likelihood × impact), not on either factor alone.

  5. In the context of information security risk management, what does the term 'vulnerability' refer to?

    Answer: A weakness that can be exploited by a threat

    A vulnerability is a weakness or gap in a system's defenses that a threat can exploit to cause harm.

  6. A project team decides to eliminate a high-risk activity from the project scope entirely. Which risk response strategy are they using?

    Answer: Risk avoidance

    Risk avoidance eliminates the risk entirely by removing the activity or changing the plan so the risk cannot occur.

  7. Which component of a comprehensive risk management plan describes the roles and responsibilities of team members in identifying and managing risks?

    Answer: Risk management roles matrix

    A risk management roles matrix (or RACI chart) clarifies who is responsible, accountable, consulted, and informed for each risk management activity.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ctc.ca.gov — Score validity · verified Oct 2026
  2. ctcexams.nesinc.com — Retake policy, test delivery, exam dates, fees, passing score, score release, test dates, time limit · verified Oct 2026