  1. During which project phase are lessons learned most effectively documented?

    Answer: Closing

    While lessons learned should be captured throughout, they are formally documented and archived during the project closing phase.

  2. A project manager uses a probability-impact matrix primarily to:

    Answer: Prioritize identified risks for response planning

    A probability-impact matrix ranks risks by combining their likelihood and potential impact, helping prioritize which risks need response plans.

  3. Which estimating technique uses historical data from a similar past project to estimate the current project's duration or cost?

    Answer: Analogous estimating

    Analogous estimating leverages actual duration or cost data from a similar previous project as the basis for the current estimate.

  4. In Agile project management, a 'velocity' metric measures:

    Answer: The amount of work a team completes in a sprint

    Velocity measures the average number of story points or work units completed by a team in a single sprint, used to forecast future output.

  5. What is the primary purpose of a project kickoff meeting?

    Answer: To align all stakeholders on project goals, roles, and expectations

    A kickoff meeting brings together key stakeholders to establish shared understanding of project objectives, deliverables, roles, and processes.

  6. When a project manager applies 'fast tracking,' they are:

    Answer: Performing activities in parallel that were originally planned sequentially

    Fast tracking compresses the schedule by overlapping phases or tasks that would normally be done in sequence, which increases risk.

  7. A stakeholder register is used to:

    Answer: Document stakeholder information, interests, and engagement levels

    The stakeholder register captures identifying information, roles, interests, expectations, and influence levels of all project stakeholders.

How this page was made: written with AI tools. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ctc.ca.gov — Score validity · verified Oct 2026
  2. ctcexams.nesinc.com — Retake policy, test delivery, exam dates, fees, passing score, score release, test dates, time limit · verified Oct 2026