What is the primary purpose of a construction project's 'punch list'?
-
A
To track daily worker attendance and payroll
-
B
To document incomplete or deficient work items that must be corrected before final payment
-
C
To list materials that need to be ordered for the next phase
-
D
To schedule subcontractor mobilization dates