A senior consultant discovers mid-project that a key vendor may be acquired, threatening delivery timelines. Which risk response strategy is MOST appropriate?
-
A
Accept the risk and document it in the risk register
-
B
Transfer the risk by requiring the vendor to post a performance bond
-
C
Develop a contingency plan with an alternate vendor while negotiating contract protections
-
D
Avoid the risk by immediately terminating the vendor contract