A senior consultant discovers mid-project that the client has added significant scope without a formal change request. What is the BEST immediate action?
-
A
Absorb the scope to maintain goodwill
-
B
Document the additional scope and initiate a formal change control process
-
C
Stop all work until the original scope is restored
-
D
Escalate directly to the client's CEO