  1. Which document formally authorizes a research project and grants the project manager authority to apply resources?

    Answer: Project charter

    The project charter is the formal document that authorizes the project and establishes the project manager's authority.

  2. A research team is experiencing scope creep on a longitudinal study. What is the BEST first step to address this?

    Answer: Review the original scope statement and submit a formal change request

    Scope creep should be managed through formal change control by reviewing the baseline scope and submitting a documented change request.

  3. In research project scheduling, what does 'float' (or slack) represent?

    Answer: The amount of time an activity can be delayed without delaying the project finish date

    Float is the amount of time a non-critical task can slip without affecting the overall project end date.

  4. A CRS researcher discovers mid-project that the original sampling frame is no longer valid due to population changes. What should they do?

    Answer: Document the issue, assess impact, and submit a formal change request

    Mid-project discoveries require documentation, impact assessment, and formal change control to maintain research integrity.

  5. What is the primary purpose of a research project's Work Breakdown Structure (WBS)?

    Answer: To decompose project deliverables into manageable components

    A WBS decomposes the total project scope into smaller, manageable work packages to facilitate planning and control.

  6. During a research project, a key subject-matter expert becomes unavailable. This is best categorized as which type of risk response?

    Answer: A risk trigger requiring a contingency plan

    Loss of a key resource is a risk trigger that should activate a pre-planned contingency response.

  7. Which estimating technique uses actual durations from similar past research projects as the primary basis for new estimates?

    Answer: Analogous estimating

    Analogous estimating relies on historical data from similar projects and is used when detailed information is limited.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. research.uams.edu — Eligibility, renewal, exam format, passing score, score release · verified Oct 2026
Research Project Management Flashcards — CRS Study Cards with Answers