Which of the following best describes the purpose of a Management of Change (MOC) procedure in a PSM program?
-
A
To document employee performance reviews after incidents
-
B
To ensure safety and hazard reviews are conducted before changes to processes, equipment, or procedures
-
C
To track spare parts inventory for critical equipment
-
D
To schedule preventive maintenance on process machinery