CRD Economic Analysis & Project Management Flashcards
6 cards from real CRD practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 CRD Economic Analysis & Project Management flashcards as text
What project management document outlines the scope of work, timeline, and deliverables for a residential geothermal installation project?
Answer: A project specification or scope of work document
A formal scope of work document defines what will be installed, when, and to what standards, protecting both the contractor and homeowner.
Which stakeholder typically issues drilling permits for vertical borehole geothermal loops in US residential projects?
Answer: The state or local well drilling regulatory authority, often the department of natural resources or environmental quality
Vertical boreholes are regulated similarly to water wells, so state or local well drilling authorities issue required permits before drilling begins.
What is the purpose of a pre-construction site assessment in residential geothermal project management?
Answer: To identify site constraints such as setbacks, utility conflicts, soil conditions, and access for drilling equipment
A pre-construction site assessment identifies physical constraints that affect loop placement, equipment access, and overall project feasibility before signing contracts.
When managing a residential geothermal project with multiple subcontractors (driller, plumber, electrician), what scheduling dependency is critical to sequence correctly?
Answer: Drilling and loop installation must be complete before the plumber connects the loop to the heat pump, which must be set before the electrician wires it
The geothermal loop must be in the ground and connected before the heat pump can be powered and tested, establishing a strict sequential dependency.
Which financial instrument specifically designed for energy efficiency upgrades allows homeowners to finance geothermal installations through their property tax assessment?
Answer: Property Assessed Clean Energy (PACE) financing
PACE financing attaches repayment to the property tax bill rather than the individual, making it accessible to homeowners who lack equity for a HELOC.
What risk management practice protects a geothermal contractor if unexpected hard rock is encountered during vertical borehole drilling?
Answer: Including a change order clause in the contract that allows additional billing for unforeseen subsurface conditions
A change order clause allows the contractor to bill for additional drilling time and materials when subsurface conditions exceed those anticipated in the original bid.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy