According to iSAQB, which activity is considered part of 'architecture evaluation'?
-
A
Measuring developer productivity using lines of code metrics
-
B
Assessing whether architectural decisions meet stakeholder concerns and quality requirements
-
C
Calculating the total cost of software licenses in the system
-
D
Reviewing the project manager's sprint planning decisions