When a company acquires a new facility that falls under OSHA PSM, the Management of Change (MOC) procedure would be LEAST applicable to which scenario?
-
A
Replacing a pump with a larger-capacity model of a different type
-
B
Replacing a pump with an identical model from the same manufacturer
-
C
Changing the operating pressure of a covered process
-
D
Introducing a new chemical substitute in an existing process