A process improvement team discovers that a key department head is actively spreading negative rumors about the initiative. According to stakeholder management best practices, what is the FIRST action the team should take?
-
A
Escalate the issue to senior leadership immediately
-
B
Schedule a one-on-one meeting to understand the department head's concerns
-
C
Send a formal written rebuttal to all staff
-
D
Remove the department head from stakeholder communications