In permitting risk management, what does a 'mitigation hierarchy' prioritize?
-
A
Avoiding impacts first, then minimizing unavoidable impacts, then compensating for residual impacts
-
B
Compensating for impacts before attempting avoidance
-
C
Minimizing costs before minimizing environmental impacts
-
D
Offsite mitigation before onsite mitigation