What is the primary purpose of outrigger pads (cribbing) when setting up a concrete pump truck?
Select your answer
A
To distribute the load over a larger ground area and prevent outrigger sinkage
B
To protect the asphalt from oil spills during operation
C
To raise the truck higher for better boom reach
D
To anchor the truck to prevent movement from concrete pressure