A project manager is asked to begin work before a project charter is approved. What is the BEST course of action?
-
A
Begin work immediately to avoid schedule delays
-
B
Request formal charter approval before committing resources
-
C
Proceed with planning but not execution
-
D
Ask the team to start low-risk tasks only