A project manager discovers that a team member has been sharing confidential client data with an unauthorized third party. What is the FIRST action the PM should take?
-
A
Immediately terminate the team member
-
B
Document the incident and report it to the appropriate authority within the organization
-
C
Warn the team member privately and monitor the situation
-
D
Inform the client directly without involving internal management