A project manager notices that the cost performance index (CPI) is 0.82 after three months. What does this indicate?
-
A
The project is 18% over budget for work completed
-
B
The project is ahead of schedule
-
C
The project has completed 82% of planned work
-
D
The project will finish 18 days late