A CPM project manager notices that two team members have conflicting tasks scheduled simultaneously in the resource plan. Which technique is used to resolve this by shifting non-critical tasks?
-
A
Resource leveling
-
B
Fast tracking
-
C
Crashing
-
D
Schedule compression