On a CPM project, the project manager identifies that a key resource is being allocated to tasks on the critical path and non-critical tasks simultaneously. The BEST first response is to:
-
A
Use resource smoothing to reallocate the resource while protecting the critical path
-
B
Immediately escalate to the project sponsor
-
C
Remove all non-critical tasks from the schedule
-
D
Replace the resource with a contractor